NH-42-EAST History

REPORT & TASK HISTORY

Full trail, still attached

Who reported, who approved, when it synced. Context stays on the task.

Daily report · Ch. 14+280

Approved

A. Mehta · Today 16:42 · Synced

Pier P7 pile cap pour completed (38 m³). Linked to WBS 4.2.1.

View match set

WBS 4.2.1 — Pier P7 pile cap

Confirmed

Progress write · Planner approved · 16:55

Marked complete from site report. Audit trail attached.

WBS 5.1.0 — Crane utilisation

Possible Risk

Conflict open · Package C booking

Idle time flagged against neighbouring package window.

Open conflict detail

Daily report · Ch. 13+050

In review

R. Singh · Today 14:10 · Synced

Embankment lift 3 complete. Compaction tests pending lab.

WBS 3.4.2 — Embankment lift 3

Review Needed

Awaiting planner · lab return

No schedule write until approval.

Prefer the weekly cut? Open milestone summary