NH-42-EAST Planner

PLANNER REVIEW

Decide what enters the schedule

AI proposed. Site engineer confirmed. Your approval writes the live plan — or not.

4
Confirmed
3
Review Needed
1
Possible Risk

WBS 5.1.0 — Crane utilisation

Possible Risk
From · A. Mehta · Ch. 14+280 Confidence 48%

Two-hour crane idle waiting rebar — may conflict with Package C booking window.

Open conflict

WBS 4.2.3 — Pier P8 rebar cage

Review Needed
From · A. Mehta · Forward note Confidence 61%

Possible 0.5 day slip if rebar truck late tomorrow. Engineer flagged for awareness.

View detail

WBS 4.2.1 — Pier P7 pile cap

Confirmed
From · A. Mehta · 38 m³ pour Confidence 92%

Pile cap pour completed. Aligns with finish window. Ready to mark progress.

WBS 3.4.2 — Embankment lift 3

Review Needed
From · R. Singh · Ch. 13+050 Confidence 74%

Lift completed to RL design. Compaction tests pending lab return.