NH-42-EAST Summary

WEEKLY / MILESTONE SUMMARY

Week 36 · Corridor progress

What the field actually did — not what last Friday’s status call hoped.

24
Reports synced
19
Approved
3
Risks open

MS-07 · Pier P7 complete

Met

Target Fri · Actual today · Cap pour confirmed

MS-08 · Pier P8 cage ready

At risk

Target Wed · Rebar delivery uncertainty · 0.5d exposure

MS-09 · Embankment to RL

Review

Lift 3 done · compaction lab pending

Structures advanced on P7. Earthworks held for lab. Crane conflict remains the single highest-urgency planner item — not yet written as a schedule slip.

Generated from approved reports only. Unapproved AI matches excluded.