WEEKLY / MILESTONE SUMMARY
What the field actually did — not what last Friday’s status call hoped.
MILESTONES
Target Fri · Actual today · Cap pour confirmed
Target Wed · Rebar delivery uncertainty · 0.5d exposure
Lift 3 done · compaction lab pending
WEEK NARRATIVE
Structures advanced on P7. Earthworks held for lab. Crane conflict remains the single highest-urgency planner item — not yet written as a schedule slip.
Generated from approved reports only. Unapproved AI matches excluded.