WBS 4.2.1 — Pier P7 pile cap
ConfirmedConfidence 92% · Progress signal · Quantity match
Pour complete aligns with planned activity finish window.
MATCH CONFIRMATION
AI proposed these task links. Confirm, edit, or reject before the planner queue.
Pier P7 pile cap pour completed (38 m³). Formwork stripped on east face. Crane idle 2 hrs waiting rebar delivery. Weather clear. Possible 0.5 day slip on P8 cage if truck late tomorrow.
PROPOSED MATCHES
Confidence 92% · Progress signal · Quantity match
Pour complete aligns with planned activity finish window.
Confidence 61% · Forward-looking delay note
Mentions possible slip if rebar truck late — flag for planner.
Confidence 48% · Idle time / resource conflict
Two-hour idle waiting delivery may collide with neighbouring package booking.
Confirmed matches enter planner review. Rejected links stay in your history only.