NH-42-EAST Planner

DELAY & CONFLICT DETAIL

Crane idle vs Package C booking

Low-confidence match with a clear operational collision. Decide with full context.

WBS 5.1.0 — Crane utilisation

Possible Risk
Confidence 48% Reported · A. Mehta Ch. 14+280

SITE NOTE

“Crane idle 2 hrs waiting rebar delivery. Weather clear.”

Overlapping booking

Package C holds tower crane 14:00–18:00 tomorrow for girder lift at Ch. 15+100.

Downstream exposure

If P8 cage slips 0.5 day, pier cap pour window shifts into reserved crane slot.

Suggested planner actions

1) Approve progress on P7 only · 2) Flag P8 as Review Needed · 3) Rebook crane or confirm Package C priority.

AUDIT TRAIL

Report submitted

A. Mehta · synced from device · 16:42

AI match proposed

Linked WBS 5.1.0 + WBS 4.2.3 · 16:43

Engineer confirmed

Both links confirmed · sent to queue · 16:51

Awaiting planner decision

Nothing written to schedule yet

Back to queue Approve with flag